An Act To Provide Energy Opportunities to Northern Maine

     Emergency preamble. Whereas, Acts of the Legislature do not become effective until 90 days after adjournment unless enacted as emergencies; and

     Whereas, the funds previously allocated to the Northern Maine Transmission Corporation Fund in the Finance Authority of Maine are essential to the viability of and to finance essential economic development in northern Maine; and

     Whereas, it is necessary that funding modifications be made as soon as possible to ensure the continuous availability of funds to carry out the Northern Maine Transmission Corporation's essential public functions; and

     Whereas, in the judgment of the Legislature, these facts create an emergency within the meaning of the Constitution of Maine and require the following legislation as immediately necessary for the preservation of the public peace, health and safety; now, therefore,

Be it enacted by the People of the State of Maine as follows:

     Sec. 1. 10 MRSA §963-A, sub-§49-H, as reallocated by RR 1999, c. 1, §11, is amended to read:

     49-H. Transmission facilities project. "Transmission facilities project" means a project approved by the Northern Maine Transmission Corporation, as established in section 9202, to carry out the purposes of chapter 1003 or any electric transmission, gas transmission, energy transfer or electric generation facility, including necessary appurtenances, otherwise proposed to the authority to benefit northern Maine.

     Sec. 2. 10 MRSA §1043, sub-§2, ¶J, as amended by PL 1999, c. 484, §6, is further amended to read:

     Sec. 3. 10 MRSA §1043, sub-§2, ¶K, as enacted by PL 1999, c. 484, §7, is amended by amending subparagraph (8) to read:

     Sec. 4. 10 MRSA §1043, sub-§2, ¶L is enacted to read:

     Sec. 5. 10 MRSA §1053, sub-§6, as repealed and replaced by PL 1999, c. 531, Pt. G, §1, is amended to read:

     6. Securities outstanding. The principal amount of revenue obligation securities the authority may have outstanding at any one time, to which subsection 5 is stated to apply in the trust agreement or other document, may not exceed an aggregate principal amount equal to $777,000,000 $877,000,000 as follows:

The amount of revenue obligation securities issued to refund securities previously issued may not be taken into account in determining the principal amount of securities outstanding, as long as proceeds of the refunding securities are applied as promptly as possible to the refunding of the previously issued securities. In computing the total amount of revenue obligation securities of the authority that may at any time be outstanding for any purpose, the amounts of the outstanding revenue obligation securities that have been issued as capital appreciation bonds or as similar instruments are valued as of any date of calculation at their then current accreted value rather than their face value.

     Sec. 6. 10 MRSA §9202, sub-§1, as enacted by PL 1999, c. 513, §6, is amended to read:

     1. Establishment and purpose. The Northern Maine Transmission Corporation is established as a body corporate and politic and public instrumentality of the State. The corporation is a special purpose corporation formed and managed as a subsidiary of the authority. The exercise by the corporation of the powers conferred by this chapter shall be is deemed the performance of essential public functions. The purpose of the corporation is to examine the need for and viability of and to finance, permit, construct, own and operate electric transmission lines necessary to connect electric utilities in the northern region of the State with the transmission grid of the United States in a manner adequate, in the opinion of the authority, to allow customers serviced by those electric utilities to receive the benefits of service similar to all other electric customers in this State.:

     Sec. 7. 10 MRSA §9202, sub-§§1-A and 1-B are enacted to read:

     1-A. Construction; other approvals. This chapter may not be interpreted to exempt the construction, ownership or operation of any project or facility from any approval required by law or rule, including but not limited to any approval required pursuant to Title 35-A, chapter 21, or to alter the franchise rights of any transmission and distribution utility.

The corporation may not finance, permit, construct, own in whole or in part or operate any electric transmission line capable of operating at 69 kilovolts or more unless the Public Utilities Commission has issued a certificate of public convenience for the construction of the line pursuant to Title 35-A, section 3132.

     1-B. Records disclosure and confidentiality. Records of the corporation, as a subsidiary of the authority, are subject to the disclosure and confidentiality provisions governing the records of the authority under section 975-A.

     Sec. 8. 10 MRSA §9203, sub-§3, as enacted by PL 1999, c. 513, §6, is amended to read:

     3. Acceptance of proposals for connections. The corporation shall request and receive proposals from public and private entities to finance, permit, construct or operate any natural gas or electric transmission lines necessary to connect electric the facilities of any transmission and distribution utilities and natural gas customers in the northern part of the State with the transmission grid of and natural gas transmission system outside of northern Maine in the United States or Canada, and may approve those proposals if they are in keeping with the intent of this chapter. If the corporation approves a project, the authority may separately consider providing financing for the project pursuant to section 1053, subsection 6, paragraph F if the proponent of the project submits a completed application to the authority.

     Sec. 9. 10 MRSA §9203, sub-§§4, 5 and 6 are enacted to read:

     4. Conduct studies. The corporation may conduct or fund such studies, including, but not limited to, feasibility studies, as may be necessary and convenient to the performance of its duties.

     5. Rulemaking. The corporation may adopt any rule, including rules establishing its bylaws, necessary or useful for carrying out any of its powers or duties. Rules adopted under this subsection may provide for fees charged for review of project applications. Rules adopted under this subsection are routine technical rules pursuant to Title 5, chapter 375, subchapter 2-A.

     6. Contracts. The corporation may enter into contracts with the authority for the provision of administrative and underwriting services.

     Sec. 10. 10 MRSA §9204, sub-§2, as enacted by PL 1999, c. 513, §6, is amended to read:

     2. Administrative expenses. Costs and expenses of maintaining, servicing and administering the fund and of performing any powers or duties under this chapter may be paid out of amounts in the fund.

     Sec. 11. 35-A MRSA §2102, sub-§2-A, as enacted by PL 1999, c. 513, §7, is repealed.

     Sec. 12. 35-A MRSA §3132, sub-§2, as amended by PL 1999, c. 398, Pt. A, §46 and affected by §§104 and 105, is further amended to read:

     2. Construction of transmission line. Except as otherwise provided in subsection 3-A, whenever any transmission and distribution utility or utilities propose to erect within this State a transmission line capable of operating at 100 kilovolts, or more, or a transmission line capable of operating at 69 kilovolts or more that is proposed to be financed, permitted, constructed, owned in whole or in part or operated by the Northern Maine Transmission Corporation pursuant to Title 10, chapter 1003 or financed by the Finance Authority of Maine pursuant to Title 10, section 1053, subsection 6, paragraph F, the utility or utilities or project proponent shall file a petition for the approval of the proposed line. The petition for approval of the proposed transmission line must contain such information as the commission by rule prescribes. The petition for approval must be set down for public hearing. The commission shall issue its order within 6 months after the petition is filed unless this period is extended either by agreement of all the parties or by the commission upon its determination that the party seeking the extension would, because of circumstances beyond that party's control, be unreasonably disadvantaged unless the extension were granted, provided that the party to that time had prosecuted its case in good faith and with due diligence.

At the time of filing of a petition for approval of a proposed line under this section, the utility shall send a copy of the petition by certified mail to the municipal officers of the municipality or municipalities in which the line is to be located.

     Sec. 13. 35-A MRSA §3132, sub-§§2-A and 2-B are enacted to read:

     2-A. Other projects requiring approval. The commission shall by rule or order adopt standards and procedures for processing an application from an applicant that is not a transmission and distribution utility for a certificate of public convenience and necessity under this section for a transmission line capable of operating at 69 kilovolts or more that is proposed to be financed, permitted, constructed, owned in whole or in part or operated by the Northern Maine Transmission Corporation pursuant to Title 10, chapter 1003 or financed by the Finance Authority of Maine pursuant to Title 10, section 1053, subsection 6, paragraph F. Except as the commission determines otherwise appropriate, the standards and procedures must conform as far as possible with those that would apply to an application from a transmission and distribution utility. Rules adopted pursuant to this subsection are routine technical rules as defined in Title 5, chapter 375, subchapter 2-A.

     2-B. Standards for certain projects. The commission may deny a certificate of public convenience and necessity for a transmission line capable of operating at 69 kilovolts or more that is proposed to be financed, permitted, constructed, owned in whole or in part or operated by the Northern Maine Transmission Corporation pursuant to Title 10, chapter 1003 or financed by the Finance Authority of Maine pursuant to Title 10, section 1053, subsection 6, paragraph F upon a finding that the line is reasonably likely to adversely affect any transmission and distribution utility or its customers.

     Emergency clause. In view of the emergency cited in the preamble, this Act takes effect when approved.

Effective June 26, 2003.

Revisor of Statutes Homepage Subject Index Search 121st Laws of Maine Maine Legislature

About the 2003 Laws Of Maine

Previous PageTop Of PageTable Of Contents

Office of the Revisor of Statutes
State House, Room 108
Augusta, Maine 04333

Contact the Office of the Revisor of Statutes