Previous PageTable Of ContentsNext Page

PUBLIC LAWS OF MAINE
First Regular Session of the 121st

CHAPTER 505
H.P. 1088 - L.D. 1483

An Act To Improve the Ability of the Public Utilities Commission To Enforce State Laws, Rules and Requirements

Be it enacted by the People of the State of Maine as follows:

     Sec. 1. 5 MRSA §10051, sub-§1, as amended by PL 2001, c. 229, §2, is further amended to read:

     1. Jurisdiction. Except as provided in section 10004; Title 8, section 279-B; Title 10, section 8003; Title 20-A, sections 10712 and 10713; Title 29-A; and Title 32, chapters 2-B, 105 and 114; and Title 35-A, section 3132, the District Court has exclusive jurisdiction upon complaint of any agency or, if the licensing agency fails or refuses to act within a reasonable time, upon complaint of the Attorney General to revoke or suspend licenses issued by the agency and has original jurisdiction upon complaint of an agency to determine whether renewal or reissuance of a license of that agency may be refused.

     Sec. 2. 5 MRSA §10051, sub-§4, as amended by PL 1999, c. 547, Pt. B, §19 and affected by §80, is repealed.

     Sec. 3. 23 MRSA §3360-A, sub-§6-C, as amended by PL 2001, c. 577, §§9 to 11, is further amended to read:

     6-C. Penalties. In an adjudicatory proceeding, the Public Utilities Commission may, in accordance with this subsection, impose an administrative penalty for any violation of this subsection. The administrative penalty may not exceed $500, except that, if the person has been found in violation of this subsection within the prior 12 months, the administrative penalty may not exceed $5,000. Administrative penalties imposed pursuant to this subsection are in addition to any other remedies or forfeitures provided by law and any liability that may result from the act or omission constituting the violation. Prior to Before imposing any penalties under this subsection, the commission shall consider evidence of the record of the violator, including, to the extent applicable, the number of successful excavations undertaken by the violator or the number of locations successfully marked by the violator during the prior 12 months. The commission may require a person who violates any provision of this section to participate, at the expense of the violator, in an educational program developed and conducted by the system.

The Public Utilities Commission may impose administrative penalties for any of the following violations:

     Sec. 4. 23 MRSA §3360-A, sub-§12, as amended by PL 1999, c. 718, §13, is further amended to read:

     12. Injunctions; costs. The owner or operator of an underground facility or may request that the Public Utilities Commission may commence an action in a court of competent jurisdiction seeking a temporary restraining issue a cease and desist order or injunction to prevent a person from undertaking an excavation that may result in damage to the underground facility. The court Public Utilities Commission may issue a temporary restraining cease and desist order or injunction if the court commission determines that the excavation or proposed excavation:

If the owner or operator prevails in an action brought pursuant to this subsection, the owner or operator is entitled to an award of the costs of bringing the action, including reasonable attorney's fees.

     Sec. 5. 25 MRSA §2933, sub-§4, as amended by PL 2001, c. 667, Pt. C, §16, is further amended to read:

     4. Penalties. On petition by the bureau, the Public Utilities Commission, in an adjudicatory proceeding, may impose the following administrative penalties for a violation by a local exchange carrier of subsection 1 or 2 or any rules adopted by the bureau implementing subsection 1 or 2:

Penalties collected by the commission under this subsection must be deposited in the Public Utilities Commission Reimbursement Fund under Title 35-A, section 117.

     Sec. 6. 25 MRSA §2933, last ¶, as enacted by PL 2001, c. 53, §2, is amended to read:

     Rules adopted pursuant to this section are routine technical rules pursuant to Title 5, chapter 375, subchapter II-A 2-A.

     Sec. 7. 35-A MRSA §112, sub-§4, ¶A, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

     Sec. 8. 35-A MRSA §112, sub-§4, ¶B, as enacted by PL 1987, c. 141, Pt. A, §6, is repealed.

     Sec. 9. 35-A MRSA §115, sub-§1, ¶D, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

     Sec. 10. 35-A MRSA §115, sub-§3, as amended by PL 1999, c. 398, Pt. A, §12 and affected by §§104 and 105, is further amended to read:

     3. Administrative penalties. Unless otherwise provided, the following provisions apply to forfeitures and administrative penalties.

     Sec. 11. 35-A MRSA §116, sub-§6, as enacted by PL 1987, c. 141, Pt. A, §6, is repealed.

     Sec. 12. 35-A MRSA §116, sub-§8, ¶D, as enacted by PL 1991, c. 591, Pt. CC, §2, is repealed.

     Sec. 13. 35-A MRSA §117, sub-§3, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

     3. Administrative penalties. Fines All administrative penalties collected by the commission which do not constitute a reimbursement of commission expenses shall must be deposited into the Public Utilities Commission Reimbursement Fund. Administrative penalties not needed to reimburse the commission for additional expenses associated with the enforcement activities that resulted in the collection of the penalty must be deposited in transferred to the General Fund of the State Treasury.

     Sec. 14. 35-A MRSA §703, sub-§4, as amended by PL 1987, c. 490, Pt. A, §2, is repealed.

     Sec. 15. 35-A MRSA §704, sub-§3, as amended by PL 1999, c. 547, Pt. B, §76 and affected by §80, is repealed.

     Sec. 16. 35-A MRSA §704, sub-§4, as enacted by PL 1987, c. 141, Pt. A, §6 and amended by PL 1999, c. 547, Pt. B, §78 and affected by §80, is further amended to read:

     4. Property loss suffered by a customer. Upon a finding by the District Court of a property loss suffered by a customer causally related to a willful or reckless violation by a public utility set out in subsection 3 of any substantive rule adopted by the commission pursuant to the authority granted in this section, the court may order the public utility to compensate the customer for the actual loss, less any set off setoff for a balance found to be due the utility by the customer for unpaid utility service. That loss may not include consequential damages. No action for damages resulting from a termination which that was in willful or reckless violation of the commissions commission's rules may be commenced until at least 60 days after notice of a claim setting forth the nature of the termination and the damages suffered has been provided to the utility. That notice shall must be provided to the utility in writing within 30 days of the termination.

     Sec. 17. 35-A MRSA §707, sub-§5, as enacted by PL 1987, c. 141, Pt. A, §6, is repealed.

     Sec. 18. 35-A MRSA §709, sub-§6, as enacted by PL 1987, c. 141, Pt. A, §6, is repealed.

     Sec. 19. 35-A MRSA c. 15 is amended by repealing the chapter headnote and enacting the following in its place:

CHAPTER 15
SANCTIONS AND ADMINISTRATIVE PENALTIES

     Sec. 20. 35-A MRSA §§1503 to 1507, as enacted by PL 1987, c. 141, Pt. A, §6, are repealed.

     Sec. 21. 35-A MRSA §1507-A is enacted to read:

§1507-A. False statements

     It is a Class C crime for any person to make or cause to be made, in any document filed with the commission or in any proceeding under this Title, any statement that, at the time and in light of the circumstances under which it is made, is false in any material respect and that the person knows is false in any material respect.

     Sec. 22. 35-A MRSA §1508, as enacted by PL 1987, c. 141, Pt. A, §6, is repealed.

     Sec. 23. 35-A MRSA §1508-A is enacted to read:

§1508-A. Administrative penalty

     1. Penalty. Unless otherwise specified in law, the commission may, in an adjudicatory proceeding, impose an administrative penalty as specified in this section.

     2. Considerations. In determining the amount of an administrative penalty under this section, the commission shall take into account:

     Sec. 24. 35-A MRSA §1509, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

§1509. Limitation on imposing penalty

     An action which that may result in the imposition of a civil or criminal an administrative penalty under this chapter shall must be commenced within 5 years after the cause of action accrues.

     Sec. 25. 35-A MRSA §1510, as enacted by PL 1989, c. 86, is repealed.

     Sec. 26. 35-A MRSA §1510-A is enacted to read:

§1510-A. Disposition of administrative penalty

     Administrative penalties collected by the commission must be deposited in the Public Utilities Commission Reimbursement Fund under section 117.

     Sec. 27. 35-A MRSA §§1511 and 1512 are enacted to read:

§1511. Revocation; suspension

     The commission may, in an adjudicatory proceeding, suspend or revoke the authority of a public utility to provide service upon a finding that the public utility is unfit to provide safe, adequate and reliable service at rates that are just and reasonable. The commission shall provide notice and a reasonable opportunity for the public utility to comply with its obligations under this Title prior to suspending or revoking the authority of a public utility to provide service pursuant to this section. The authority granted in this section is in addition to the commission's authority under section 1321.

§1512. Unauthorized service

     The commission may order any person to cease and desist from providing service if it finds that the person has not obtained commission authorization to provide the service as required by this Title. The commission may impose the sanctions and penalties of this chapter upon any person that provides service without first obtaining commission authorization as required by this Title.

     Sec. 28. 35-A MRSA §2102, sub-§1, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

     1. Approval required. Except as provided in subsection 2 and in section 4507, no a public utility may not furnish any of the services set out in section 2101 in or to any municipality in or to which another public utility is furnishing or is authorized to furnish a similar service without the approval of the commission. The commission may condition approval upon the submission of a bond or other financial security if the commission determines that such a requirement is necessary to ensure that a public utility has the financial ability to meet its obligations under this Title.

     Sec. 29. 35-A MRSA §3203, sub-§7, as enacted by PL 1997, c. 316, §3, is repealed and the following enacted in its place:

     7. Penalties. The commission may impose administrative penalties upon a competitive electricity provider in accordance with chapter 15.

     Sec. 30. 35-A MRSA §3206-A, sub-§1, as enacted by PL 1999, c. 398, Pt. G, §4, is amended to read:

     1. Penalties. The commission shall require an investor-owned transmission and distribution utility to divest an affiliated competitive provider if the commission determines in an adjudicatory proceeding that:

The commission may impose administrative penalties of up to $100,000 for a violation of section 3205 or section 3206 or any rule adopted by the commission pursuant to those sections. Each day of a violation constitutes a separate offense. In addition, the commission may require disgorgement of profits or revenues realized as a result of a violation of section 3205 or section 3206 or any rule adopted by the commission pursuant to those sections. Penalties collected by the commission under this section must be deposited in the Public Utilities Commission Reimbursement Fund under section 117.

     Sec. 31. 35-A MRSA §4512, sub-§1, as enacted by PL 1987, c. 141, Pt. A, §6, is repealed.

     Sec. 32. 35-A MRSA §4512, sub-§2, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

     2. Damages. In addition to the forfeiture provided in subsection 1 administrative penalty imposed pursuant to this Title, a natural gas pipeline utility that fails to comply with an order of the commission shall reimburse any person whose property is damaged as a result of the failure for the amount of the property damage; and be liable in double damages for any injury resulting to a person from the failure.

     Sec. 33. 35-A MRSA §4515, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

§4515. Cease and desist orders

     A The commission may order a natural gas pipeline utility to cease and desist from operating or acting in violation of a statute or rule or order of the commission may be enjoined from the operation or action upon complaint addressed to the Superior Court and brought by the commission. Whenever practicable, the commission shall notify a natural gas pipeline utility against whom an action for injunctive relief a cease and desist order is contemplated and afford it an opportunity to present its views and, except in the case of a knowing and willful violation, shall afford it reasonable opportunity to comply. Failure to notify and afford such an opportunity does not preclude the granting of appropriate relief.

     Sec. 34. 35-A MRSA §4516, as amended by PL 1993, c. 113, §1, is repealed.

     Sec. 35. 35-A MRSA §4516-A is enacted to read:

§4516-A. Administrative penalty

     1. Violation of this Title. The commission may impose an administrative penalty on a natural gas pipeline utility that violates any provision of this Title relating to safety of pipeline facilities or transportation of gas or any rule issued under this Title in an amount not to exceed $100,000 for each violation. Each day of violation constitutes a separate offense.

     2. Maximum administrative penalty. The maximum administrative penalty may not exceed $1,000,000 for any related series of violations.

     3. Determining amount of penalty. In determining the amount of the penalty, the commission shall consider the following:

     4. Payment of penalty. The amount of the administrative penalty may be:

     5. Limitation on imposing penalty. Any action that may result in the imposition of an administrative penalty pursuant to this section must be commenced within 5 years after the cause of action accrues.

     Sec. 36. 35-A MRSA §4704, as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

§4704. Cease and desist orders

     A The commission may order a gas utility to cease and desist from operating or acting in violation of a statute or rule or order of the commission may be enjoined from the operation or action upon complaint addressed to the Superior Court and brought by the commission. Whenever practicable, the commission shall notify a gas utility against whom an action for injunctive relief a cease and desist order is contemplated and afford it an opportunity to present its views and, except in the case of a knowing and willful violation, shall afford it reasonable opportunity to comply. Failure to notify and afford such an opportunity does not preclude the granting of appropriate relief.

     Sec. 37. 35-A MRSA §4705, as amended by PL 1993, c. 113, §2, is repealed.

     Sec. 38. 35-A MRSA §4705-A is enacted to read:

§4705-A. Administrative penalty

     1. Violation of this Title. The commission may impose an administrative penalty on a gas utility that violates any provision of this Title relating to safety of gas facilities or any rule issued under this Title in an amount not to exceed $100,000 for each violation. Each day of violation constitutes a separate offense.

     2. Maximum administrative penalty. The maximum administrative penalty may not exceed $1,000,000 for any related series of violations.

     3. Determining amount of penalty. In determining the amount of the penalty, the commission shall consider the following:

     4. Payment of penalty. The amount of the penalty may be:

     5. Limitation on imposing penalty. Any action that may result in the imposition of an administrative penalty pursuant to this section must be commenced within 5 years after the cause of action accrues.

     Sec. 39. 35-A MRSA §7105, sub-§3, as enacted by PL 1991, c. 654, §4 and affected by §5, is repealed.

     Sec. 40. 35-A MRSA §7106, sub-§2, ¶A, as enacted by PL 1997, c. 702, §1, is amended to read:

     Sec. 41. 35-A MRSA §7106, sub-§2, ¶C, as enacted by PL 1997, c. 702, §1, is repealed.

     Sec. 42. 35-A MRSA §7106, sub-§2, ¶D is enacted to read:

     Sec. 43. 35-A MRSA §7107, sub-§3, as enacted by PL 1999, c. 59, §1 and affected by §3, is repealed.

     Sec. 44. 35-A MRSA §7107, sub-§3-A is enacted to read:

     3-A. Denial or revocation of registration; notice. The commission may by order, after notice and opportunity for hearing, deny, suspend or revoke an application for registration as, or the registration of, a service provider or billing aggregator if the commission finds that the order is in the public interest and that the applicant or registrant, or a principal of the applicant or registrant:

     Sec. 45. 35-A MRSA §7107, sub-§5, as enacted by PL 1999, c. 59, §1 and affected by §3, is amended to read:

     5. Enforcement authority. In addition to any authority the commission may have pursuant to other law, the commission may enforce this section in accordance with this subsection.

Penalties collected by the commission under this subsection must be deposited in the General Fund.

Effective September 13, 2003, unless otherwise indicated.

Revisor of Statutes Homepage Subject Index Search 121st Laws of Maine Maine Legislature

About the 2003 Laws Of Maine

Previous PageTop Of PageTable Of ContentsNext Page

Office of the Revisor of Statutes
State House, Room 108
Augusta, Maine 04333

Contact the Office of the Revisor of Statutes