| 2.__Retainage.__In any contract awarded for a public |
improvement, the owner of a public improvement may retain 5% of |
the money due the contractor until substantial completion of the |
work.__At substantial completion, the owner and the contractor |
shall inspect the work and prepare a punch list.__The owner may |
thereafter withhold for defective or incomplete work only those |
funds that are sufficient to account for 1.5 times the value of |
punch list work.__As punch list work is completed, the retainage |
held by the owner must be correspondingly reduced.__Funds may not |
be retained in anticipation of warranty claims but may be |
retained as directed by the contractor's surety or as necessary |
to account for liquidated damages or other contract defaults as |
determined by the designer. |