LD 1403
pg. 7
Page 6 of 8 An Act To Create an Alternative Method of Dispute Resolution in Homeowner Claim... Page 8 of 8
Download Bill Text
LR 685
Item 1

 
§8556.__Release; insurance

 
1.__Action barred.__If a claimant accepts an offer under
section 8554 and the contractor fulfills the offer:

 
A.__The claimant is barred from bringing an action for the
claim described in the notice of claim under section 8554,
subsection 1; and

 
B.__The contractor is deemed for insurance purposes to have
been legally obligated to make the repairs or the monetary
payment as if the claimant had recovered a judgment against
the contractor in the combined amount of the cost of any
repairs and the amount of any monetary payment. The repairs
and monetary payment under this paragraph are enforceable as
a judicial settlement but do not constitute a legal judgment
against the contractor for the purposes of obtaining
insurance coverage or submitting a competitive bid.

 
2.__Exception for code violations.__Notwithstanding the
provisions of subsection 1, if a construction defect that gave
rise to the notice of claim involves a violation of a legally
enforceable building code, including, but not limited, to a state
or local building, electrical, plumbing or other code, or the
provisions of Title 10, chapter 951 and if after the homeowner
accepts an offer made in compliance with this chapter by the
contractor and the contractor fulfills that offer the violation
is not corrected, the homeowner may bring an action for that
portion of the claim described in the notice of claim that
involves the violation.

 
§8557.__Contract of sale; provisions

 
1.__Notice required.__Upon entering into a contract for the
design, development, construction, sale or construction and sale
of a residence; for the repair of a new or existing residence; or
for the construction, alteration, addition or repair of an
appurtenance to a new or existing residence in which the contract
amount exceeds the amount requiring a home construction contract
pursuant to Title 10, chapter 219-A, the contractor must provide
written notice to the homeowner of the contractor's right to
resolve alleged construction defects before a homeowner may
commence litigation against the contractor under this chapter.
The notice required by this section must be conspicuous and may
be included as part of the contract.

 
2.__Form of notice.__The notice required by subsection 1 must
be in substantially the following form:


Page 6 of 8 Top of Page Page 8 of 8