| 2.__Retainage.__In a contract awarded for a public |
improvement, the public owner may retain 5% of the money due |
the contractor until substantial completion of the work.__At |
substantial completion, the owner and the contractor shall |
inspect the work and prepare a punch list.__The owner may, |
after inspection of the work, withhold for defective or |
incomplete work only those funds that are sufficient to |
account for 1.5 times the value of punch list work.__As punch |
list work is completed, the retainage held by the owner must |
be correspondingly reduced.__Funds may not be retained in |
anticipation of warranty claims but may be retained as |
directed by the contractor's surety or as necessary to account |
for liquidated damages or other contract defaults as |
determined by the designer. |