131st MAINE LEGISLATURE |
|
|
LD 957 |
|
LR 1151(04) |
|
|
|
An Act Requiring
Water Bottle Filling Stations in New and Renovated Public Schools |
|
Fiscal Note for
Senate Amendment " " to Committee Amendment "A" |
|
Sponsor: Sen. Rotundo of Androscoggin |
|
Fiscal Note Required: Yes |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Note |
State Mandate - funded in fiscal year 2024-25, unfunded after
fiscal year 2024-25
|
|
|
|
FY 2023-24 |
FY 2024-25 |
Projections FY 2025-26 |
Projections FY 2026-27 |
Net Cost
(Savings) |
|
|
|
|
|
|
General Fund |
|
$0 |
$1,404 |
$0 |
$0 |
|
|
|
|
|
|
|
Appropriations/Allocations |
|
|
|
|
|
|
General Fund |
|
$0 |
$1,404 |
$0 |
$0 |
|
|
|
|
|
|
|
State Mandates |
|
|
|
|
|
|
Required Activity |
Unit Affected |
Local Cost |
|
Requires new
public schools and public schools undergoing substantial renovations to be
equipped with water bottle filling stations beginning in fiscal year 2024-25. |
School |
$1,560 = 100% |
|
The required
local activities in this bill may represent a state mandate pursuant to the
Constitution of Maine. If the bill does require a local unit of government to
expand or modify its activities so as to necessitate additional expenditures
from local revenue, the state mandate provisions of the Constitution of Maine
require either: (1) General Fund appropriations be provided to fund at least
90% of any additional necessitated local costs of the mandate; or (2) a
Mandate Preamble be added to the bill and two-thirds of the members of each
House vote to exempt the mandate from the funding requirement. If the bill
does represent a state mandate and neither one of these actions occurs, the
local units of government will not be required to implement the mandated
activities. |
Fiscal Detail
and Notes |
|
|
|
|
|
|
This amendment
includes a one-time General Fund appropriation of $1,404 in fiscal year
2024-25 to a newly established State Mandate Reimbursement - Water Bottle
Filling Stations program within the Department of Education to reimburse
school administrative units for 90% of the cost of installing water bottle
filling stations when constructing a new public school building or undergoing
a substantial renovation to an existing school building. This estimate
assumes 2 water bottle filling stations will be installed in one newly
constructed school building and one substantially renovated school building
per year at a cost of $390 per unit.