HP1011
LD 1472
Session - 128th Maine Legislature
C "A", Filing Number H-643, Sponsored by
LR 1486
Item 3
Bill Tracking, Additional Documents Chamber Status

Amend the bill by striking out everything after the enacting clause and before the summary and inserting the following:

Sec. 1. 35-A MRSA §2503, sub-§2,  as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

2. Notice.   The applicant may give public notice of the application by publishing its description of the proposed facility once in a newspaper circulated in the municipality or municipalities encompassing the limits of the proposed location. The applicant shall send a copy of any application filed with the Department of Transportation to the municipal clerk of each municipality in which the facilities are located, or to the clerk of the county commissioners in the case of facilities within an unorganized township, except that the applicant may, without publication of its application, place its facility described in its application on receipt of a permit from the licensing authority as may be otherwise provided. If a proposed facility is located underground and is in excess of 500 feet in length, the applicant shall, within 5 business days of submitting an application to the applicable licensing authority, provide the ConnectME Authority established in Title 5, section 12004-G, subsection 33-F a notice that includes a description and the location of the proposed facility.

Sec. 2. 35-A MRSA §9204-A, sub-§6-A  is enacted to read:

6-A Notice of construction.   The authority shall disseminate information about a proposed underground facility that it receives in accordance with section 2503, subsection 2 in a manner that is accessible to all parties that may be interested in installing a broadband conduit in the area of the proposed underground facility.

SUMMARY

This amendment replaces the bill. It requires an applicant for a permit for a proposed underground facility in excess of 500 feet in length to provide notice to the ConnectME Authority. Notice must include a description and the location of the proposed project and must be provided within 5 business days of submitting an application with the applicable licensing authority. The ConnectME Authority is required to disseminate the information it receives regarding the underground facility in a manner that ensures all parties that may be interested in installing a broadband conduit have access to that information.

FISCAL NOTE REQUIRED
(See attached)