127th MAINE LEGISLATURE |
|
|
LD 1676 |
|
LR 2794(08) |
|
|
|
An Act To
Establish a Process for Procurement of Renewable Resources |
|
Fiscal Note for
Senate Amendment " " to Committee Amendment "A" |
|
Sponsor: Sen. Woodsome of York |
|
Fiscal Note Required: Yes |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Note |
|
|
|
|
|
|
|
|
|
|
FY 2015-16 |
FY 2016-17 |
Projections FY 2017-18 |
Projections FY 2018-19 |
Net Cost
(Savings) |
|
|
|
|
|
|
General Fund |
|
$13,400,000 |
$0 |
$0 |
$0 |
|
General Fund - Maine Budget
Stabilization Fund
|
|
$0 |
($6,700,000) |
($6,700,000) |
$0 |
|
|
|
|
|
|
|
Appropriations/Allocations |
|
|
|
|
|
|
Other Special Revenue Funds |
|
$0 |
$6,700,000 |
($6,700,000) |
$0 |
|
|
|
|
|
|
|
Transfers |
|
|
|
|
|
|
General Fund |
|
($13,400,000) |
$0 |
$0 |
$0 |
|
General Fund - Maine Budget
Stabilization Fund
|
|
$0 |
$6,700,000 |
$6,700,000 |
$0 |
|
Other Special Revenue Funds |
|
$13,400,000 |
($6,700,000) |
($6,700,000) |
$0 |
|
|
|
|
|
|
|
Fiscal Detail
and Notes |
|
|
|
|
|
|
This amendment
eliminates the $6,700,000 transfer from the Maine Budget Stabilization Fund
to the Cost Recovery Fund within the Public Utilities Commission (PUC) in
both fiscal year 2016-17 and 2017-18 and instead directs $13,400,000 to be
transferred from the unappropriated surplus of the General Fund at the close
of fiscal year 2015-16 following certain statutorily required transfers (the
so-called "cascade"). There is no guarantee that there will be
sufficient funds from the unappropriated surplus of the General Fund to make
this transfer. The amendment allows up to 50% of funds within the Cost
Recovery Fund to go to facilities serving the Northern Maine Independent
System Administrator region. This amendment also allows the PUC to not enter
into any contract if a determination from the PUC is made that none of the
bids are competitive. The amendment requires any funds remaining in the Cost
Recovery Fund at the close of fiscal year 2016-17 be transferred to the Maine
Budget Stabilization Fund. |
|
The amendment
also adds an emergency preamble and clause, as well as eliminates the
requirement that the PUC conduct a solicitation to procure certain energy. |
|
|
|
|
|
|
|