127th MAINE LEGISLATURE
LD 558 LR 964(01)
An Act To Amend the Community-based Renewable Energy Project Laws for Purposes of the Mayo Mill Project
Preliminary Fiscal Impact Statement for Original Bill
Sponsor: Rep. Higgins of Dover-Foxcroft
Committee: Energy, Utilities and Technology
Fiscal Note Required: No
             
Preliminary Fiscal Impact Statement
Minor cost increase - Other Special Revenue Funds
Fiscal Detail and Notes
Any additional costs to the Public Utilities Commission to increase the total allowable installed generating capacity of all community-based renewable energy pilot program participants combined from 50 megawatts to 60 megawatts are expected to be minor and can be absorbed within existing budgeted resources.