An Act Regarding Energy Infrastructure Development
PART A
Sec. A-1. 5 MRSA §12004-G, sub-§30-D is enacted to read:
Public Utilities | Interagency Review Panel | Expenses Only | 35-A MRSA §122, sub-§1-B |
Sec. A-2. 35-A MRSA §122, as enacted by PL 2007, c. 656, Pt. A, §3, is amended to read:
§ 122. Energy infrastructure corridors
(1) Generation interconnection transmission facilities;
(2) Energy generation facilities; or
(3) Electric transmission and distribution facilities or energy transport pipelines that cross an energy infrastructure corridor or are within an energy infrastructure corridor for a distance of less than 5 miles.
(1) The Searsport-Loring corridor may be used, developed and expanded for energy infrastructure consistent with any leases, easements or other agreements in effect on the effective date of this subsection. It is not a statutory corridor until the expiration or termination of such leases, easements or other agreements.
(2) The executive director of the Loring Development Authority of Maine shall notify the Interagency Review Panel under subsection 1-B when any leases, easements or other agreements in effect on the effective date of this subsection affecting or otherwise pertaining to the Searsport-Loring corridor have expired or otherwise terminated.
(1) The Director of the Governor's Office of Energy Independence and Security within the Executive Department or the director's designee;
(2) The Commissioner of Administrative and Financial Services or the commissioner's designee;
(3) The commissioner of each department or the director of any other state agency or authority that owns or controls land or assets within the statutory corridor under consideration or that commissioner's or director's designee; and
(4) Four members of the public appointed by the Governor in accordance with this subparagraph, subject to review by the joint standing committee of the Legislature having jurisdiction over utilities and energy matters and to confirmation by the Senate:
(a) One member with expertise in energy and utilities selected from candidates nominated by the President of the Senate;
(b) One member with expertise in real estate or finance selected from candidates nominated by the President of the Senate;
(c) One member representing industrial or commercial energy consumers selected from candidates nominated by the Speaker of the House; and
(d) One member representing residential energy consumers selected from candidates nominated by the Speaker of the House.
Public members serve 3-year terms, except that a vacancy must be filled for the unexpired portion of the term. A public member serves until a successor is appointed. A public member may serve a maximum of 2 consecutive terms. Compensation of public members is as provided in Title 5, section 12004G, subsection 30D.
(1) The panel shall negotiate the terms of the occupancy agreement, including but not limited to the length of the agreement and compensation to the State for use of the statutory corridor and any conditions of use. In negotiating the occupancy agreement, the panel shall take into account existing legal commitments, contractual obligations, reasonable investment-backed expectations and relevant prior state investments, when applicable.
(2) Compensation to the State may be in the form of payments made on an annual basis or the functional or financial equivalent, discounted prices for energy products or services, partial ownership by the State of the energy infrastructure on the basis of the value of the statutory corridor in proportion to the energy infrastructure as a whole, or other appropriate form. The terms of compensation may include provisions for periodic adjustment of the compensation to the State over time and reimbursement of costs to any state agency or authority that owns or controls land or assets within the statutory corridor.
(3) Negotiation of compensation to the State must be based on at least one independent appraisal performed by a professional appraiser in accordance with paragraph F. An independent appraisal performed under this subparagraph must, at a minimum, consider the costs that will be avoided by the potential developer, including but not limited to the costs of acquisition, lease or rental of private land, the costs of property taxes on private land, the costs of surveying, appraisal, environmental, engineering and other work necessary for use of private land, the costs of time and potential conflict regarding the use of private land, the unique and limited nature of the state-owned land or asset, the revenues estimated to be generated by the use of the state-owned land or asset and other relevant factors.
(4) Any occupancy agreement entered into under this section for the use of any portion of the Interstate 95 corridor that is designated as the Maine Turnpike must comply with the memorandum of agreement between the Department of Transportation and the Maine Turnpike Authority pursuant to subsection 1C.
(1) Have demonstrated experience in the valuation and evaluation of utility corridors or transportation corridors;
(2) Hold a professional designation from a nationally recognized organization of appraisers; and
(3) Be licensed by this State as a certified general real property appraiser in accordance with Title 32, section 14035 or hold a comparable license from another state.
The cost of the services of a professional appraiser who provides services in accordance with this paragraph must be paid by potential developers submitting proposals for use of the corridor under this subsection in proportion to the amount of time spent by the appraiser on each potential developer's proposal.
(1) Proprietary information in the possession of the state agency or authority; and
(2) Proprietary information in the possession of the panel or a professional appraiser assisting the panel.
(1) Application of reasonable engineering standards of the Maine Turnpike Authority to the location and design of energy infrastructure on Maine Turnpike Authority property within the Interstate 95 statutory corridor;
(2) The right of the Maine Turnpike Authority to review and approve all construction, reconstruction, expansion, improvement, maintenance or operation of energy infrastructure on Maine Turnpike Authority property as part of the Interstate 95 statutory corridor in accordance with reasonable engineering standards of the Maine Turnpike Authority. The Maine Turnpike Authority may not unreasonably withhold approval under this subparagraph;
(3) The right of the Maine Turnpike Authority to require relocation or reconfiguration of any portion of energy infrastructure and all related installations on Maine Turnpike Authority property within the Interstate 95 statutory corridor at the sole cost of the owner of the energy infrastructure so affected when and to the extent that such relocation or reconfiguration is reasonably necessary for the construction, reconstruction, expansion, improvement, maintenance or operation of the Maine Turnpike;
(4) The right of the Maine Turnpike Authority to regulate access to Maine Turnpike Authority property within the Interstate 95 statutory corridor in a reasonable manner that is consistent with the safe and proper administration of the Maine Turnpike as a limited access highway; and
(5) Reimbursement to the Maine Turnpike Authority of any reasonable costs it may incur in relation to use of the Maine Turnpike as part of the Interstate 95 statutory corridor, including, but not limited to, reasonable costs of review and inspection of design, construction, maintenance or repair of energy infrastructure and related operational costs, including, but not limited to, those for traffic control and other measures that are required to accommodate construction, maintenance or repair of energy infrastructure.
(1) Materially enhances or does not harm transmission opportunities for energy generation within the State;
(2) Is reasonably likely to reduce electric rates or other relevant energy prices or costs for residents and businesses within the State relative to the value of those rates, prices or costs but for the proposed energy infrastructure development or, if the deciding authority is unable to determine to its satisfaction the impact of the proposal on rates, prices or costs, the owner or operator of the proposed energy infrastructure agrees to pay annually an amount of money, determined by the deciding authority, to reduce rates, prices or costs over the life of the proposed energy infrastructure; and
(3) Is in the long-term public interest of the State, based on a determination made in accordance with paragraph B.
(1) Materially enhances or does not harm transmission opportunities for energy generation within the State;
(2) Is reasonably likely to reduce electric rates or other relevant energy prices or costs for residents and businesses within the State relative to the expected value of those electric rates or other energy prices or costs but for the proposed energy infrastructure development;
(3) Increases long-term economic benefits for the State, including but not limited to direct financial benefits, employment opportunities and economic development;
(4) Ensures efficient use of the statutory corridor through collocation of energy infrastructure, collaboration between energy infrastructure developers and the preservation of options for future uses;
(5) Minimizes conflict with the public purposes for which the state-owned land or asset is owned and any management plans for the land or asset within the statutory corridor and, when necessary, mitigates unavoidable impacts;
(6) Limits and mitigates the effects of energy infrastructure on the landscape, including but not limited to using underground installation when economically and technically feasible;
(7) Increases the energy reliability, security and independence of the State; and
(8) Reduces the release of greenhouse gases.
(1) The rulemaking to designate an energy infrastructure a petitioned corridor must include a public hearing in which any member of the public may submit oral or written testimony or comments, which must be incorporated into the rule-making record in accordance with Title 5, section 8052, subsection 1. The commission shall provide an opportunity for examination of the petitioner at a rule-making hearing. The commission shall allow for written comments by any member of the public up to 7 days prior to the hearing. The commission shall allow a second round of written comments to be filed within 10 days of the hearing or within such longer time as the commission may direct.
(2) In any rulemaking regarding the designation of an energy infrastructure a petitioned corridor, the commission shall address all written comments, including those submitted pursuant to subsection 3, and state its rationale for adopting or rejecting any proposals or recommendations contained in those written comments.
(3) A designation of an energy infrastructure a petitioned corridor must be based on substantial evidence in the record of the rule-making hearing.
(1) Does not contain sufficient information to support the designation of an energy infrastructure a petitioned corridor; or
(2) Was filed by a person other than the Office of the Public Advocate, Executive Department, Governor's Office of Energy Independence and Security or an interested person as defined by subsection 1, paragraph E a person listed in paragraph B.
(1) In the public interest, including, but not limited to, consideration of:
(a) Encouraging colocation collocation of energy infrastructure;
(b) Enhancing the efficient utilization of existing energy infrastructure; and
(c) Limiting impacts on the landscape; and
(2) Consistent with environmental and land use laws and rules of the State. A finding that the future development of energy infrastructure within the petitioned corridor is reasonably likely to be consistent with environmental and land use laws and rules of the State under this paragraph has no evidentiary value in a subsequent consolidated environmental permit proceeding undertaken by the department pursuant to subsection 6.
(1) Houlton Band Trust Land, as defined in Title 30, section 6203, subsection 2A;
(2) Passamaquoddy Indian territory, as defined in Title 30, section 6203, subsection 6;
(3) Penobscot Indian territory, as defined in Title 30, section 6203, subsection 9;
(4) Aroostook Band Trust Land, as defined in Title 30, section 7202, subsection 2;
(5) Lands that constitute a park as defined in Title 12, section 1801, subsection 7 and Baxter State Park; and
(6) Federally owned land . ; and
(7) The Maine Turnpike, as described in Title 23, section 1964, subsection 9.
(1) The commission has issued a certificate of public convenience and necessity approving the transmission line in accordance with section 3132; and
(2) The department has issued a consolidated environmental permit approving the project in accordance with subsection 6.
(1) The commission has issued a corridor use certificate approving the project in accordance with subsection 5; and
(2) The department has issued a consolidated environmental permit approving the project in accordance with subsection 6.
(1) The commission has issued a corridor use certificate approving the project in accordance with subsection 5; and
(2) The department has issued a consolidated environmental permit approving the project in accordance with subsection 6.
(1) The person has entered into an occupancy agreement with the Interagency Review Panel in accordance with subsection 1B and, if applicable, with the Maine Turnpike Authority in accordance with subsection 1C, and in compliance with applicable state and federal rules, regulations and laws;
(2) The department has issued a consolidated environmental permit for the project in accordance with subsection 6; and
(3) If the project is a transmission line that requires a certificate of public convenience and necessity under section 3132, the commission has issued a certificate of public convenience and necessity for the transmission line.
(1) The department has issued a consolidated environmental permit for the project in accordance with subsection 6;
(2) The commission has issued a corridor use certificate for the project in accordance with subsection 5-A; and
(3) If the project is a transmission line that requires a certificate of public convenience and necessity under section 3132, the commission has issued a certificate of public convenience and necessity approving the transmission line.
(1) Minimize utility rates or increase the reliability of utility service;
(2) Have the net effect of reducing the release of greenhouse gases; or
(3) Enhance economic development within the State.
If the department receives an application for a permit to develop or construct energy infrastructure within an energy infrastructure corridor prior to adopting a rule to implement this subsection, the department shall process the application in accordance with the department's existing review and permitting procedures.
(1) Lands or easements located within 300 feet of an inhabited dwelling;
(2) Lands or easements on or adjacent to any developed or undeveloped water power;
(3) Lands or easements so closely paralleling existing wire lines of other utilities or existing energy transport pipelines that the proposed energy infrastructure would substantially interfere with service rendered over the existing lines or pipelines, except with the consent of the owners;
(4) Lands or easements owned or used by railroad corporations, except as authorized pursuant to section 2311;
(5) Lands or easements owned by the State or an agency or authority of the State; and
(6) Transmission and distribution plant that is owned, controlled, operated or managed by a transmission and distribution utility on the effective date of this section.
(1) The commission may exercise the authority under this paragraph only in an adjudicatory proceeding upon a petition by the Office of the Public Advocate or the Executive Department, Governor's Office of Energy Independence and Security demonstrating that such action is urgently needed to avoid substantial harm to electricity consumers regarding anticipated activity associated with an energy infrastructure corridor. A determination by the commission that the exercise of eminent domain under this paragraph is urgently needed to avoid substantial harm to electricity consumers regarding anticipated activity associated with an energy infrastructure corridor constitutes reviewable final agency action.
(2) The amount of any lands or easements taken by the commission pursuant to this subsection may be no greater than is required to avoid the harm to electricity consumers identified under subparagraph (1).
(3) The right of eminent domain granted in this paragraph does not apply to personal property, fixtures or improvements that constitute transmission and distribution plant or an energy transport pipeline.
(4) The commission may exercise the right of eminent domain for the purposes of this paragraph in the same manner and under the same conditions as set forth in chapter 65. For the purposes of the exercise of eminent domain authorized by this paragraph, the commission is both a person and the State.
(5) The commission is authorized to assess transmission and distribution utilities to the extent necessary to obtain sufficient funds to pay for lands and easements taken pursuant to this subsection.
(6) The commission, in an adjudicatory proceeding upon petition by the Office of the Public Advocate or the Executive Department, Governor's Office of Energy Independence and Security, may transfer or convey to any person or state agency or authority lands and easements once acquired, except that a transmission and distribution utility or the owner of an energy transport pipeline whose lands or easements were taken pursuant to this paragraph must be given the first opportunity to acquire the lands or easements to the extent necessary or useful in the performance of its duties as a transmission and distribution utility or an owner of an energy transport pipeline.
(7) The commission shall report on the circumstances of any taking by eminent domain to the joint standing committee of the Legislature having jurisdiction over utilities and energy matters during the next regular session of the Legislature following the acquisition of lands or easements by eminent domain.
Sec. A-3. 35-A MRSA §3131, sub-§4-A is enacted to read:
(1) Is not a generator interconnection transmission facility as defined in section 3132, subsection 1B; and
(2) Is not constructed primarily to provide electric reliability, as determined by the commission.
Sec. A-4. 35-A MRSA §3132, sub-§6, as amended by PL 2009, c. 309, §3, is further amended to read:
Sec. A-5. 35-A MRSA §3132, sub-§6-A is enacted to read:
Sec. A-6. PL 2009, c. 372, Pt. F, §5, as amended by PL 2009, c. 415, Pt. E, §1, is repealed.
Sec. A-7. Staggered terms. Notwithstanding the Maine Revised Statutes, Title 35-A, section 122, subsection 1-B, paragraph A, subparagraph (4), the Governor shall appoint the initial public members of the Interagency Review Panel to serve staggered terms. Of the initial appointees, one member serves an initial term of one year, one member serves an initial term of 2 years and 2 members serve initial terms of 3 years. An initial term of one or 2 years may not be considered a full term for purposes of limiting the number of terms for which a member may serve.
Sec. A-8. Report. Within existing resources, the Executive Department, Governor's Office of Energy Independence and Security, in consultation with agencies with relevant expertise, including but not limited to the Department of Environmental Protection, the Public Utilities Commission, the Department of Transportation and the Department of Defense, Veterans and Emergency Management, Maine Emergency Management Agency, and with interested parties, shall prepare a report on issues affecting the collocation of electric transmission and distribution facilities, natural gas transmission lines, carbon dioxide pipelines and other energy infrastructure. The report must include an analysis of the safety, health, engineering, environmental, geotechnical, land use and other factors that restrict or otherwise affect collocation of such facilities. The office shall review and include in the report its findings with respect to practices in other jurisdictions as well as any industry or governmental recommendations regarding collocation of such facilities. The office shall include in the report a description of how its analysis and findings apply to energy infrastructure corridors as defined in the Maine Revised Statutes, Title 35-A, section 122. By February 1, 2011, the office shall submit its report to the joint standing committee of the Legislature having jurisdiction over utilities and energy matters and the Interagency Review Panel established under Title 35A, section 122 and to all state agencies with permitting authority over energy infrastructure, including but not limited to the Department of Environmental Protection, the Maine Land Use Regulation Commission, the Public Utilities Commission and the Department of Transportation.
PART B
Sec. B-1. 5 MRSA §282, sub-§9, as enacted by PL 2009, c. 372, Pt. F, §3, is repealed and the following enacted in its place:
Sec. B-2. 23 MRSA §4210-E is enacted to read:
§ 4210-E. Transportation Efficiency Fund
Sec. B-3. 35-A MRSA §10103, sub-§4, as enacted by PL 2009, c. 372, Pt. B, §3, is amended to read:
Sec. B-4. 35-A MRSA §10103, sub-§4-A is enacted to read:
(1) Seventy-five percent for energy efficiency initiatives; and
(2) Twenty-five percent for alternative energy resources initiatives; and
As part of the annual report required under section 10104, subsection 5, the director shall report on the use of revenues from the energy infrastructure benefits fund. The report must document the revenues transferred from the energy infrastructure benefits fund to the trust during the most recently completed fiscal year and the current fiscal year and amounts and uses of money expended by the trust in accordance with this subsection during the most recently completed and the current fiscal year.
Sec. B-5. Transition; funding for public members of the Interagency Review Panel. Notwithstanding any other provision of law, until sufficient revenues from the energy infrastructure benefits fund are transferred to the Efficiency Maine Trust pursuant to the Maine Revised Statutes, Title 5, section 282, subsection 9 to compensate public members of the Interagency Review Panel pursuant to Title 5, section 12004G, subsection 30D, program funds of the Efficiency Maine Trust from other sources may be used for that purpose.
Sec. B-6. Transportation efficiency and alternative energy resources initiatives; working groups. The Executive Department, Governor's Office of Energy Independence and Security, referred to in this section as "the office," shall convene 2 working groups in accordance with this section to examine and make recommendations regarding transportation efficiency initiatives and alternative energy resources initiatives funded by the revenues collected in the energy infrastructure benefits fund established in the Maine Revised Statutes, Title 5, section 282, subsection 9.
1. The office shall convene a working group on transportation efficiency initiatives. The group must include, but is not limited to, a representative of the Department of Transportation, a representative of the Department of Environmental Protection and a representative of the Efficiency Maine Trust. The working group shall examine and make recommendations regarding the allocation of revenues from the energy infrastructure benefits fund for transportation-related purposes and the uses of the Transportation Efficiency Fund established in Title 23, section 4210-E. The working group shall submit its findings and recommendations no later than March 1, 2011 to the joint standing committees of the Legislature having jurisdiction over transportation matters and over utilities and energy matters.
2. The office shall convene a working group on alternative energy resources initiatives. The group must include, but is not limited to, a representative of the Efficiency Maine Trust, a representative of a statewide environmental advocacy organization and a representative of renewable energy consultants. The working group shall examine and make recommendations regarding the allocation of revenues from the energy infrastructure benefits fund pursuant to Title 5, section 282, subsection 9 to the Efficiency Maine Trust and the uses of those revenues according to Title 35-A, section 10103, subsection 4-A for alternative energy resources initiatives. The working group shall submit its findings and recommendations no later than March 1, 2011 to the joint standing committees of the Legislature having jurisdiction over transportation matters and over utilities and energy matters.
Sec. B-7. Appropriations and allocations. The following appropriations and allocations are made.
TRANSPORTATION, DEPARTMENT OF
Transportation Efficiency Fund N106
Initiative: Establishes the Transportation Efficiency Fund.
OTHER SPECIAL REVENUE FUNDS | 2009-10 | 2010-11 |
All Other
|
$0 | $500 |
OTHER SPECIAL REVENUE FUNDS TOTAL | $0 | $500 |
PART C
Sec. C-1. 2 MRSA §9, sub-§3, ¶C, as amended by PL 2009, c. 372, Pt. H, §2, is further amended to read:
Sec. C-2. 2 MRSA §9, sub-§4 is enacted to read:
Nothing in this subsection alters any of the responsibilities or limits any of the authority of the Department of Administrative and Financial Services, Bureau of General Services pursuant to Title 5. Nothing in this subsection alters or limits the ability of departments or agencies of the State, along with the Bureau of General Services pursuant to Title 5, to generate or cogenerate energy at state facilities for use on site and elsewhere.
Sec. C-3. 35-A MRSA §3132, sub-§13, as amended by PL 2009, c. 123, §6, is further amended to read:
A person who has bought, leased or otherwise been conveyed any interest in public land for the purpose of constructing a transmission line may not undertake construction of that line except under the terms of the certificate of public convenience and necessity as originally issued for that transmission line by the commission or as modified by order of the Department of Environmental Protection under subsection 7 or under the terms of an amended certificate of public convenience and necessity issued by the commission or deemed to have been issued by the commission under subsection 11-A.
As used in this subsection, "public land" means land that is owned or controlled by the State, by an instrumentality of the State or by a political subdivision of the State.
As used in this subsection, "future interest or option to purchase an interest in land" includes an option, purchase and sale agreement or other equivalent legal instrument that conveys the intent to pursue a future sale, lease or other conveyance of land.
Sec. C-4. Legislative review; implementation. The joint standing committee of the Legislature having jurisdiction over utilities and energy matters shall review the implementation of this Act during the First Regular Session of the 125th Legislature. Based on its review, the joint standing committee may submit a bill relating to this Act to the First Regular Session of the 125th Legislature.
Sec. C-5. Department of Transportation report. By January 15, 2011, the Department of Transportation shall report to the joint standing committees of the Legislature having jurisdiction over transportation matters and utilities and energy matters regarding current and potential uses of abandoned railroad corridors owned or controlled by the department for energy infrastructure development.