SP0215
LD 678
Signed on 2007-05-22 - First Regular Session - 123rd Legislature - Text: MS-Word, RTF or PDF LR 762
Item 1
Bill Tracking Chamber Status

An Act To Limit the Eminent Domain Authority of a Transmission and Distribution Utility

Be it enacted by the People of the State of Maine as follows:

Sec. 1. 35-A MRSA §3136, sub-§5  is enacted to read:

5 Commission approval; certificate of public convenience and necessity.   Notwithstanding the authority granted in this section, a transmission and distribution utility may not take by right of eminent domain lands and easements necessary for the location of a transmission line that requires commission approval pursuant to section 3132 unless it has received a certificate of public convenience and necessity from the commission pursuant to section 3132 approving the construction, rebuilding or relocation of the transmission line.

summary

This bill requires a transmission and distribution utility to obtain approval for the construction, rebuilding or relocation of a transmission line pursuant to the Maine Revised Statutes, Title 35-A, section 3132 before it exercises its eminent domain authority for lands and easements relating to the location of the transmission line.


Top of Page