Item 1

 
Northern Maine Transmission Corporation pursuant to Title 10,
chapter 1003 or financed by the Finance Authority of Maine pursuant
to Title 10, section 1053, subsection 6, paragraph F, the utility
or utilities or project proponent shall file a petition for the
approval of the proposed line. The petition for approval of the
proposed transmission line must contain such information as the
commission by rule prescribes. The petition for approval must be
set down for public hearing. The commission shall issue its order
within 6 months after the petition is filed unless this period is
extended either by agreement of all the parties or by the
commission upon its determination that the party seeking the
extension would, because of circumstances beyond that party's
control, be unreasonably disadvantaged unless the extension were
granted, provided that the party to that time had prosecuted its
case in good faith and with due diligence.

 
At the time of filing of a petition for approval of a proposed
line under this section, the utility shall send a copy of the
petition by certified mail to the municipal officers of the
municipality or municipalities in which the line is to be
located.

 
Sec. 13. 35-A MRSA §3132, sub-§§2-A and 2-B are enacted to read:

 
2-A. Other projects requiring approval.__The commission shall
by rule or order adopt standards and procedures for processing an
application from an applicant that is not a transmission and
distribution utility for a certificate of public convenience and
necessity under this section for a transmission line capable of
operating at 69 kilovolts or more that is proposed to be
financed, permitted, constructed, owned in whole or in part or
operated by the Northern Maine Transmission Corporation pursuant
to Title 10, chapter 1003 or financed by the Finance Authority of
Maine pursuant to Title 10, section 1053, subsection 6, paragraph
F.__Except as the commission determines otherwise appropriate,
the standards and procedures must conform as far as possible with
those that would apply to an application from a transmission and
distribution utility.__Rules adopted pursuant to this subsection
are routine technical rules as defined in Title 5, chapter 375,
subchapter 2-A.

 
2-B.__Standards for certain projects.__The commission may deny
a certificate__of public convenience and necessity for a
transmission line capable of operating at 69 kilovolts or more
that is proposed to be financed, permitted, constructed, owned in
whole or in part or operated by the Northern Maine Transmission
Corporation pursuant to Title 10, chapter 1003 or financed by the
Finance Authority of Maine pursuant to Title 10, section 1053,
subsection 6, paragraph F upon a finding that the line is
reasonably likely to adversely affect any transmission and
distribution utility or its customers.


Page 8 of 10 Top of Page Page 10 of 10
Related Pages
  Search Bill Text Legislative Information
Bill Directory Search
Bill
Status
Session Information
119th Legislature Bills Maine Legislature

Office of Legislative Information
100 State House Station
Augusta, ME 04333
voice: (207) 287-1692
fax: (207) 287-1580
tty: (207) 287-6826
Word Viewer for Windows Disclaimer