| 1.__Basis for variance.__The board may grant a variance from | the sand supply standard in section 480-D, subsection 7 for the | following only: |
|
| A.__Reconstruction or replacement of a building located in | a V-zone, as described in section 480-E, subsection 9, due | to involuntary destruction by fire or other cause, except | for an ocean storm; or |
|
| B.__Height restrictions for new structures or additions to | existing structures for the purpose of raising an existing | building above the flood elevation, provided the increase | in height is no more than the minimum necessary to meet | flooding requirements. |
|
| | 2.__Requirements.__In order to obtain a variance, the | applicant must demonstrate, by clear and convincing evidence, | that: |
|
| A.__There is no feasible alternative to the proposed | variance; |
|
| B.__Because of unusual design characteristics or site | conditions, the project will be consistent with the intent | of the board; |
|
| C.__If the variance is granted, the project will not cause | harm to real or personal property not owned by the | applicant; and |
|
| D.__Even if the proposed variance is granted, all other | statutory criteria set forth in section 480-D will be met. |
|
| | This bill prohibits seawall construction and enlargement; | prohibits reconstruction of buildings in the sand dune system | damaged by more than 50% by a storm; prohibits construction of | new buildings in the frontal dune; and authorizes the Board of | Environmental Protection to grant variances from sand supply | standards. |
|
|