Resolve, Directing the Development of a Building Code and Building Rehabilitation Code Implementation Plan

Sec. 1. Maine building code and building rehabilitation code implementation plan. Resolved: That the Executive Department, State Planning Office, with assistance from the Office of the State Fire Marshal, the Department of Economic and Community Development and the Maine Historic Preservation Commission, collectively referred to in this resolve as "the agencies," shall develop a plan for implementing the Maine Model Building Code and the International Existing Building Code; and be it further

Sec. 2. Duties. Resolved: That in the development of the plan, the agencies shall consider the following:

1. What agency should provide oversight and administration of the codes;

2. How code updates should be handled;

3. Outreach, communication and technical assistance to municipalities;

4. Training and certification of code officers, architects and builders;

5. Enforcement and appeal procedures;

6. Estimated costs to implement mandatory codes;

7. Projected costs for code administration;

8. Funding options for initial implementation and ongoing administration;

9. Identification of overlap between codes;

10. Guidance to municipalities regarding overlap between codes;

11. If rulemaking or statutory changes are needed to facilitate certain kinds of development, such as development of historic properties;

12. Phase-in dates for code adoption by service center communities, nonservice center communities with codes and towns adopting codes for the first time; and

13. Funding or incentives to put codes in place; and be it further

Sec. 3. Public participation. Resolved: That in developing the plan the agencies shall solicit input from interested parties, including, but not limited to, other state agencies, the Maine Municipal Association, groups representing Maine building officials and inspectors, builders, architects, engineers, real estate developers and public safety officials; and be it further

Sec. 4. Completion date; report. Resolved: That the agencies shall complete the development of the implementation plan by January 15, 2008. The report must include a recommended implementation schedule. The Executive Department, State Planning Office shall report to the Joint Standing Committee on Business, Research and Economic Development by February 15, 2008 with the results of the implementation plan development. The Joint Standing Committee on Business, Research and Economic Development is authorized to submit legislation relating to the report to the Second Regular Session of the 123rd Legislature.

summary

This resolve is a recommendation of the Community Preservation Advisory Committee. The bill directs the Executive Department, State Planning Office, with assistance from the Office of the State Fire Marshal, the Department of Economic and Community Development and the Maine Historic Preservation Commission, to develop a plan for implementing the Maine Model Building Code and the International Existing Building Code.